The Big Art Field Guide

How to prepare a site brief for large-scale public art

Give artists and delivery partners a usable site packet: context, access, known constraints, responsible people and the questions that need professional review.

For Municipal site owners, parks teams, developers, campuses and nonprofit installation hosts

Planning guidance by Big Art Partners

Latest source review · Individual review dates are listed below.

Name the site owner and approval route

NYC’s artwork-installation guidance asks teams working on or over city-owned property to contact Percent for Art before determining artist selection. It also distinguishes agency approval from Public Design Commission review. This is a local process example: a supportive project sponsor and the party responsible for a site may have different roles. [1]

Big Art Partners recommends a cover sheet naming the owner, operating department, project sponsor and day-to-day contact. Ask those parties to confirm the review route and which decisions each can authorize. Record the proposed display period and any construction or event dates that may affect access. Leave unconfirmed approvals explicitly open.

Questions for your project brief

Big Art Partners planning checklist

  • BAP deliverable: a site authority sheet and approvals tracker.

Show the place as people will experience it

DC’s FY26 Public Art Building Communities checklist requests site photographs and plans, artwork shown in context, and site-owner support that addresses installation and maintenance. These requirements offer a concrete example of a site submission that joins visual information with operational responsibility. [2]

For a BAP project brief, we recommend a labeled photo set showing approach routes, nearby uses and the intended viewing area. Add an annotated plan with the proposed artwork zone, entrances, existing furniture and landscaping. Describe who uses the space and what the host wants them to experience; distinguish a quiet viewing site from a gathering place or an interactive installation.

Questions for your project brief

Big Art Partners planning checklist

  • BAP deliverable: a photo-and-plan packet with a concise audience and use statement.

Gather access and utility information without guessing

Boston’s public-art proposal guidance asks for installation and deinstallation details, required equipment, lighting and sound plans, and a project schedule. It also separates permission from the department controlling the site from artwork design review. [3]

BAP recommends asking the site team to mark delivery access, staging possibilities, working-hour restrictions and the contacts responsible for power, water or data where relevant. Attach existing records with their dates and authors. Route unknown ground conditions, attachment capacity, underground services and equipment access to the appropriate site and delivery professionals. The briefing task is to expose these questions; it is not to provide engineering specifications.

Questions for your project brief

Big Art Partners planning checklist

  • BAP deliverable: an access-and-services questionnaire with an owner for each unknown.

Assign care, inspection and public reporting

Boston’s conservation program connects each artwork’s care plan to defined treatments, responsible parties and financial obligations. It also provides a public route for reporting damage. [4]

BAP recommends involving the people who will operate the site before the artwork is selected. Ask who can inspect it, who can authorize specialist maintenance and where the operating budget sits. For light, sound or interactive work, record proposed hours and the person responsible for shutdown or service issues. Ask the artist and relevant specialists to define the appropriate care information for the actual work.

Questions for your project brief

Big Art Partners planning checklist

  • BAP deliverable: a care-responsibility sheet and incident contact list.

Turn the packet into a decision-ready brief

BAP recommends a final joint review by the host, artist and proposed delivery team. Sort each open item into information needed for artist selection, information needed for design development and information needed before installation. Give each item an owner and a due date. Record what the team can responsibly price now and what requires a site visit or paid specialist work. The resulting packet should support a useful shortlist and a scoped next phase, with the limitations of the current information easy to find.

Questions for your project brief

Big Art Partners planning checklist

  • BAP deliverable: a dated site brief, marked drawings and a prioritized questions register.
  • Update the packet when the site, artwork or intended duration changes.

Sources & review dates

  1. NYC Public Design Commission: Artwork Installation ↗ · Reviewed
  2. DC Commission on the Arts and Humanities: FY26 PABC document checklist ↗ · Reviewed
  3. Boston Mayor’s Office of Arts and Culture: Public Art Policy (2024) ↗ · Reviewed
  4. City of Boston: Public Art Conservation ↗ · Reviewed